Navigate Up
Sign In
Select a Project:
Construction Update Header

Project 3: Washington St - Cedar Lake Rd to Hainesville Road

Limits:
Reconstruct Washington St from Cedar Lake Rd to just west of Hainesville Rd.
Resurface Cedar Lake Rd from approximately 500' south and 100' north of Washington Street.
Reconstruct 100' of Dorothy Lane just west of Washington St.

Project Description:
This project consists of widening to three lanes and reconstructing Washington St and adding a right turn lane and resurfacing Cedar Lake Rd.

Other features of the project include bike lanes added to both sides of the
pavement, sidewalks, watermain replacement, sanitary replacement and
landscaping.


Project Status: Active

Percent Complete: 75 %

Current Information:

Washington St. will be reopened to traffic the week of July 21, likely on or before Thursday, July 24. The closure allowed the contractor to construct the watermain, drainage, aggregate base, curbs and most of the pavement. There were also some delays caused by unanticipated conflicting utilities that needed to be relocated. Thank you for your patience during the closure.

The contractor will continue to work on the project through mid-August placing the final surface, remaining sidewalks, landscaping and punchlist. This will be done under one lane traffic control using flaggers during the day as necessary.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:
Jeff Garth, V3 Companies
Resident Engineer
847.546.3255

Additional Contact(s):
Scott Aho, LCDOT
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400
 
Lake County Traffic Info:
www.lakecountypassage.com

Project Website:
www.washingtonstreetinfo.com

Construction Update Header

Project 5: Delany Rd

Limits:
From Sunset Ave To York House Rd

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

 

Construction Update Header

Project 6: River Road and Roberts Road Intersection Improvements

Limits:
About 900 feet in each direction of the intersection of River and Roberts Roads in Lake Barrington. 

Project Description:
This intersection improvement project consists of replacing the existing signalized intersection with a roundabout. The work that will be done includes pavement widening and resurfacing, storm sewer, drainage and pavement shoulder improvements, and replacement of an existing 42 inch diameter culvert under River Road. The project also includes construction of a 7 foot high retaining wall, street lights, landscaping, new sidewalks and a new multi-use path connection to the Lake County Forest Preserve District path at the Fox River Forest Preserve.

Poor soil conditions make it necessary to stabilize the ground under the new intersection to provide a solid roadway foundation. This stabilization process will require time and it will be necessary to close River Road to all traffic while this work takes place. Roberts Road will remain open to traffic during construction, with the exception of a 2-3 week full intersection closure in 2015.


Project Status: Scheduled

Percent Complete: 0 %

Current Information:

The construction schedule for the River Road and Roberts Road roundabout has been modified as a result of several factors including utility relocation delays and a soil stabilization subcontractor conflict. The general construction staging plan will remain the same; a pre-stage will occur this year in order to complete part of stage one with the remaining stage one work to begin next spring.

For the pre-stage work this year, the plan is to close River Road (Roberts Road will remain open) beginning August 11, 2014 so the contractor can complete the majority of the soil stabilization work. This closure is expected to last until late November/early December of this year. At that time, it's planned for crews to install temporary pavement for River Road and temporary signals at the intersection so we can open the roadway and intersection for the winter.

In spring of 2015, the contractor will be back in to build the roundabout. River Road will again be closed to traffic so construction of stages one and two can be completed; Roberts Road will remain open to traffic. For stage three, both River and Roberts will be closed for about 20 days to complete the final elements of the roundabout.

The detour routes for all stages remain the same and can be found on the Detours page of the website. The construction staging information can be found on the Schedule page of the website. As always, please feel free to contact us with any questions regarding the project.  

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Jeff Dayson, LCDOT
Resident Engineer
847.865.0151

Additional Contact(s):
Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com

Project Website:
riverroberts.com

Date: 7/29/2014

Construction Update Header

Project 7: Winchester Road at Metra Railroad

Limits:
Beginning 800 feet west of the Metra rail crossing to 200 feet west of Ellis Av in the Village of Libertyville

Project Description:
Winchester Road will be widened to accommodate a left turn lane into the west entrance of the Lake County Libertyville campus, and a left turn lane/relocation of the entrance to the north parking area of Libertyville's Butler Lake Park. This project will require a 14-day closure of Winchester Road beginning at 6am June 5.


Project Status: Active

Percent Complete: 99 %

Current Information:

This project is nearing completion. All that remains are cleanup and punch list items that will be addressed in the coming weeks.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Dan Martinez, LCDOT
Resident Engineer
847.377.7400
 
Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400
 
Lake County Traffic Info:
Construction Update Header

Project 8: Peterson Rd From US 45 To West of IL 83

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 9: O'Plaine Road from Washington Street to IL137

Limits:
From just north of IL137 to just south of Washington St in Green Oaks, Waukegan and Gurnee.

Project Description:
This project consists of asphalt resurfacing and the installation of bike-friendly shoulders. One lane traffic control will be used during daytime construction.


Project Status: Active

Percent Complete: 95 %

Current Information:

Final Pavement Markings have been completed and punch list work items are all that remain to finalize the project.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Randy DeRue, LCDOT
Resident Engineer
847.377.7400
 
Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400
 
Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 10: Fairfield Road, Gossell Rd to IL60

Limits:
From just north of Gossell Rd to just south of IL60 in Wauconda and unincorporated Lake County.

Project Description:
This project consists of asphalt resurfacing and the installation of bike-friendly shoulders. One lane traffic control will be used during daytime construction.


Project Status: Complete

Percent Complete: 100 %

Current Information:

Project Completed

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Randy DeRue, LCDOT
Resident Engineer
847.377.7400

Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 11: Riverwoods Road, IL60 to IL22

Limits:
From just north of IL22 to just south of IL60, in Lincolnshire and Mettawa.

Project Description:
This project consists of asphalt resurfacing and the installation of bike-friendly shoulders. One lane traffic control will be used during daytime construction.


Project Status: Active

Percent Complete: 98 %

Current Information:

The project is nearing completion. Punchlist items need to be completed. Expect minimal backups.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Pete Torola, LCDOT
Resident Engineer
847.377.7400

Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 12: Washington Street, from US41 to IL131

Limits:
From just east of the US41 bridge to IL131 in Waukegan and Park City.

Project Description:
This project consists of asphalt resurfacing. Lane closures will be used during daytime construction.


Project Status: Complete

Percent Complete: 100 %

Current Information:

Project is complete.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 13: Grass Lake Rd From East of Grass Lake Bridge To IL 59

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 14: Russell Rd From IL 131 To Kenosha Rd

Limits:
From IL131 (Green Bay Road) to Kenosha Road in the city of Zion.

Project Description:
This project consists of asphalt resurfacing and the installation of bike friendly shoulders. One lane traffic control will be used during daytime construction.


Project Status: Active

Current Information:

Project is scheduled to start on 8/25/2014. The first items of work will be culvert and storm sewer work. This will be followed by removing the top layer of asphalt. Expect minor backups during these operations.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Pete Torola, LCDOT
Resident Engineer
847.377.7400

Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
 
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com
 
Construction Update Header

Project 15: Sand Lake Rd

Limits:
From Grand Ave (IL132) to US45 in Lindenhurst

Project Description:
The project consists of asphalt resurfacing and the installation of bike friendly shoulders. One lane traffic control will be used during daytime construction.


Project Status: Scheduled

Percent Complete: 0 %

Current Information:

Work will begin on August 11th, following LindenFest. The contractor is planning on starting with curb improvements.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Dan Martinez, LCDOT
Resident Engineer
847.377.7400
 
Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400
 
Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 16: Lewis Ave From Dugdale St To IL 137

Limits:
From 500' north of Argonne Dr to IL137 in North Chicago

Project Description:
This project consists of asphalt resurfacing. Lane closures will be used during daytime construction.


Project Status: Scheduled

Percent Complete: 0 %

Current Information:

This project is expected to start in early September and is expected to  take about a month and a half to complete.

 

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:
Pete Torola, LCDOT
Resident Engineer
847.377.7400

Additional Contact(s):
Glenn Petko, LCDOT
Engineer of Construction
Resident Engineer
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com
 
Construction Update Header

Project 17: Midlothian Rd From South of Winchester Rd To IL 176

Limits:
South of Winchester Rd to IL 176 in the village of Mundelein

Project Description:
This project consists of asphalt pavement removal and replacement, pavement markings, curb and gutter replacement and installation of ADA ramps on the east side of Midlothian. A southbound bypass lane will also be installed at Cambridge Rd. One lane traffic control will be used during daytime construction.


Project Status: Active

Percent Complete: 0 %

Current Information:

Weather permitting, work will begin the week of September 2 and project is expected to be complete by end of October. Daily intermittent lane closures will be in place during the construction, drivers are cautioned to watch for workers and equipment. Thank you for your patience.​

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:
Randy DeRue, LCDOT
Resident Engineer
847.740.3449

Additional Contact(s):
Glenn Petko, LCDOT
Engineer of Construction
Resident Engineer
847.377.7400
 
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com
 
Construction Update Header

Project 18: Long Grove Rd

Limits:
From Ela Road to east of Deer Valley Drive (west of Quentin Rd) in the village of Deer Park.

Project Description:
This project consists of asphalt resurfacing of pavement and bike lanes, replacement of driveway culverts and addition of side street drainage crossings.


Project Status: Active

Percent Complete: 31 %

Current Information:

Grinding of the roadway is complete. The grinding revealed that patching of the bike lanes was required. LCDOT policy provides additional time for patching. Delays were caused by additional sewer work and utility conflicts.

The first of two layers of asphalt is expected to be paved late August. Concurrently, the removal and replacement of driveways will occur. The second layer of asphalt will be paved followed by final pavement markings and landscaping.

Expected finish: Late September 2014
 
Drivers and bicyclists can expect delays due to daytime lane closures.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Paul Guardi, LCDOT
Resident Engineer
847.865.0151

Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 19: Aptakisic Road Adaptive Signal Control

Limits:
From Brandywyn Lane to Parkway Drive

Project Description:
Includes modification of the intersection cabinets and traffic detector configuration of existing traffic signals along Aptakisic Road in Lincolnshire and Buffalo Grove.


Project Status: Scheduled

Percent Complete: 0 %

Current Information:

Work is scheduled to begin mid-July and be complete in the fall of 2014

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Scott Aho, LCDOT
Resident Engineer
847.377.7400
 
Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400
 
Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 20: Gilmer Rd From Midlothian Rd To Fremont Center Rd

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 21: Gilmer Rd From Wildlife Way

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 22: Fairfield Rd

Limits:
North of IL60 to south of IL120 - Starting 0.3 miles north of IL60 to 0.2 miles south of Townline Rd in unincorporated Lake County.

Project Description:
This project consists of the removal and replacement of three retaining walls. One lane of traffic in each direction will be maintained during most of the construction.


Project Status: Active

Percent Complete: 50 %

Current Information:

Work on west side of Fairfield is complete. Contractor has now made a lane shift to the east and moved traffic to the west to allow work to be done on the east side of Fairfield.

Expect scattered and periodic traffic delays due to temporary lane closures caused by construction activities.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Matt Mitchell, LCDOT
Resident Engineer
847.377.7400
 
Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400
 
Lake County Traffic Info:
lakecountypassage.com

 
Construction Update Header

Project 23: Washington Street Drainage Project

Limits:
At southeast corner of Washington St and IL83

Project Description:
This project consists of repairing an existing pipe drain crossing under Washington St and the installation of new storm sewer along the south side of Washington St.


Project Status: Complete

Percent Complete: 100 %

Current Information:

Project is Complete

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Pete Torola, LCDOT
Resident Engineer
847.377.7400

Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 24: Rollins Rd

Limits:
From Helendale Ave to Wilson Rd in unincorporated Lake County.

Project Description:
The project consists of asphalt resurfacing and installation of curb and gutter on south side of Rollins Rd and other drainage improvements. The project also includes installation of storm sewer, pavement widening, and the reconstruction of the existing bike path.


Project Status: Scheduled

Percent Complete: 0 %

Current Information:

Project scheduled to start August 11,2014.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Scott Stalesky, LCDOT
Resident Engineer
847.377.7400

Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400

Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 25: Lewis Ave From Blanchard Rd

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 26: NS Bikepath From Union Pacific Railroad To East of US 41

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 27: Washington St From Atkinson Rd To Lancer Ln

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 28: Cedar Lake Rd From Washington St To S Rosedale Ct

Limits:
Washington Street to Park Road in Round Lake

Project Description:
This project installs a sidewalk and related items on the east side of Cedar Lake Rd


Project Status: Scheduled

Percent Complete: 0 %

Current Information:

Work is scheduled to begin in mid-summer and be complete in the fall of 2014.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Scott Aho, LCDOT
Resident Engineer
847.377.7400
 
Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400
 
Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 29: Hunt Club Road Sidewalk

Limits:
From IL132 (Grand Ave) to West Brook Lane in Gurnee.

Project Description:
This project consists of the installation of sidewalk, pedestrian signals and crosswalks on the east side of Hunt Club Road.


Project Status: Active

Percent Complete: 80 %

Current Information:

The work consists of construction of a 5 foot wide concrete sidewalk along the east side of Hunt Club Road. Additionally the concrete median islands on the north side of the intersection will be modified to accommodate a pedestrian crossing for the north leg. Removing and replacing the stop bar and cross walk pavement markings is included.

The project is expected to be complete this summer.

Like us on FacebookFollow us on Twitter

Construction Map

Construction Information:

Scott Aho, LCDOT
Resident Engineer
847.377.7400
 
Additional Contact(s):

Glenn Petko, LCDOT
Engineer of Construction
847.377.7400
Al Giertych, LCDOT
Assistant County Engineer
847.377.7400
 
Lake County Traffic Info:
lakecountypassage.com
Construction Update Header

Project 30: Aptakisic Rd From Weiland Rd To Bond St

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 31: Peterson Rd From W. of IL 83 To West of Alleghany Rd

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 32: Alleghany Rd

Limits:
From Peterson Rd To IL Rte 120

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 33: Washington St

Limits:
From West of Hainesville Rd to Haryan Way

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 34: Washington St From Haryan Way To Lake St

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 35: Hawley St From East of US 45 To Midlothian Rd

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 36: O'Plaine Rd From Kennedy Dr - South of IL 120

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 37: Deerfield Rd

Limits:
IL Rte. 45 To Saunders Rd.

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 38: Arlington Heights Rd

Limits:
Lake Cook Rd To IL Rte 83

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map

Construction Update Header

Project 39: Buffalo Grove Rd

Limits:
Deerfield Pkwy To IL Rte 22

Project Status: Scheduled

Like us on FacebookFollow us on Twitter

Construction Map


Contact Us
Parking and Directions
Website Disclaimer
Site Map
Lake County, Illinois
847.377.2000
18 N. County Street
Waukegan, IL 60085
About Our County
PASSAGE
Alert Lake County
Find Help