    Project 3: Washington St - Cedar Lake Rd to Hainesville Road

    Limits:
    Reconstruct Washington St from Cedar Lake Rd to just west of Hainesville Rd.
    Resurface Cedar Lake Rd from approximately 500' south and 100' north of Washington Street.
    Reconstruct 100' of Dorothy Lane just west of Washington St.

    Project Description:
    This project consists of widening to three lanes and reconstructing Washington St and adding a right turn lane and resurfacing Cedar Lake Rd.

    Other features of the project include bike lanes added to both sides of the
    pavement, sidewalks, watermain replacement, sanitary replacement and
    landscaping.


    Project Status: Active

    Percent Complete: 75 %

    Current Information:

    Washington St. will be reopened to traffic the week of July 21, likely on or before Thursday, July 24. The closure allowed the contractor to construct the watermain, drainage, aggregate base, curbs and most of the pavement. There were also some delays caused by unanticipated conflicting utilities that needed to be relocated. Thank you for your patience during the closure.

    The contractor will continue to work on the project through mid-August placing the final surface, remaining sidewalks, landscaping and punchlist. This will be done under one lane traffic control using flaggers during the day as necessary.

  •  

    Date: 8/7/2014 8:10 AM

    Project 5: Delany Rd

    Limits:
    From Sunset Ave To York House Rd

    Project Status: Scheduled

  • Construction Information:

    Jeff Dayson, LCDOT
    Resident Engineer
    847.865.0151

    Additional Contact(s):
    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400

    Lake County Traffic Info:
    lakecountypassage.com

    Project Website:
    riverroberts.com

    Date: 8/5/2014 3:10 PM

    Project 6: River Road and Roberts Road Intersection Improvements

    Limits:
    About 900 feet in each direction of the intersection of River and Roberts Roads in Lake Barrington. 

    Project Description:
    This intersection improvement project consists of replacing the existing signalized intersection with a roundabout. The work that will be done includes pavement widening and resurfacing, storm sewer, drainage and pavement shoulder improvements, and replacement of an existing 42 inch diameter culvert under River Road. The project also includes construction of a 7 foot high retaining wall, street lights, landscaping, new sidewalks and a new multi-use path connection to the Lake County Forest Preserve District path at the Fox River Forest Preserve.

    Poor soil conditions make it necessary to stabilize the ground under the new intersection to provide a solid roadway foundation. This stabilization process will require time and it will be necessary to close River Road to all traffic while this work takes place. Roberts Road will remain open to traffic during construction, with the exception of a 2-3 week full intersection closure in 2015.


    Project Status: Scheduled

    Percent Complete: 0 %

    Current Information:

    The construction schedule for the River Road and Roberts Road roundabout has been modified as a result of several factors including utility relocation delays and a soil stabilization subcontractor conflict. The general construction staging plan will remain the same; a pre-stage will occur this year in order to complete part of stage one with the remaining stage one work to begin next spring.

    For the pre-stage work this year, the plan is to close River Road (Roberts Road will remain open) beginning August 11, 2014 so the contractor can complete the majority of the soil stabilization work. This closure is expected to last until late November/early December of this year. At that time, it's planned for crews to install temporary pavement for River Road and temporary signals at the intersection so we can open the roadway and intersection for the winter.

    In spring of 2015, the contractor will be back in to build the roundabout. River Road will again be closed to traffic so construction of stages one and two can be completed; Roberts Road will remain open to traffic. For stage three, both River and Roberts will be closed for about 20 days to complete the final elements of the roundabout.

    The detour routes for all stages remain the same and can be found on the Detours page of the website. The construction staging information can be found on the Schedule page of the website. As always, please feel free to contact us with any questions regarding the project.  

  • Construction Information:

    Dan Martinez, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:

    Date: 7/31/2014 12:27 PM

    Project 7: Winchester Road at Metra Railroad

    Limits:
    Beginning 800 feet west of the Metra rail crossing to 200 feet west of Ellis Av in the Village of Libertyville

    Project Description:
    Winchester Road will be widened to accommodate a left turn lane into the west entrance of the Lake County Libertyville campus, and a left turn lane/relocation of the entrance to the north parking area of Libertyville's Butler Lake Park. This project will require a 14-day closure of Winchester Road beginning at 6am June 5.


    Project Status: Active

    Percent Complete: 99 %

    Current Information:

    This project is nearing completion. All that remains are cleanup and punch list items that will be addressed in the coming weeks.

  • Date: 7/31/2014 12:27 PM

    Project 8: Peterson Rd From US 45 To West of IL 83

    Project Status: Scheduled

  • Construction Information:

    Randy DeRue, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

    Date: 7/31/2014 12:27 PM

    Project 9: O'Plaine Road from Washington Street to IL137

    Limits:
    From just north of IL137 to just south of Washington St in Green Oaks, Waukegan and Gurnee.

    Project Description:
    This project consists of asphalt resurfacing and the installation of bike-friendly shoulders. One lane traffic control will be used during daytime construction.


    Project Status: Active

    Percent Complete: 95 %

    Current Information:

    Final Pavement Markings have been completed and punch list work items are all that remain to finalize the project.

  • Construction Information:

    Randy DeRue, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

    Date: 7/31/2014 12:27 PM

    Project 10: Fairfield Road, Gossell Rd to IL60

    Limits:
    From just north of Gossell Rd to just south of IL60 in Wauconda and unincorporated Lake County.

    Project Description:
    This project consists of asphalt resurfacing and the installation of bike-friendly shoulders. One lane traffic control will be used during daytime construction.


    Project Status: Active

    Percent Complete: 65 %

    Current Information:

    Additional milling work added to accommodate continuous 1 1/2" HMA surface paving from IL60 to Gossell Rd. Work will begin after the Independence Day holiday.

  • Construction Information:

    Pete Torola, LCDOT
    Resident Engineer
    847.377.7400

    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400

    Lake County Traffic Info:
    lakecountypassage.com

    Date: 8/1/2014 8:01 AM

    Project 11: Riverwoods Road, IL60 to IL22

    Limits:
    From just north of IL22 to just south of IL60, in Lincolnshire and Mettawa.

    Project Description:
    This project consists of asphalt resufacing and the installation of bike-friendly shoulders. One lane traffic control will be used during daytime construction.


    Project Status: Active

    Percent Complete: 55 %

    Current Information:

    Storm sewer and minor ditch work will be completed next. This will be followed by shoulder gravel installation and final landscaping. The final pavement surface will be placed in about a week or two. Expect traffic delays and watch for workers and flaggers during these operations.

  • Date: 7/31/2014 12:27 PM

    Project 12: Washington Street, from US41 to IL131

    Limits:
    From just east of the US41 bridge to IL131 in Waukegan and Park City.

    Project Description:
    This project consists of asphalt resurfacing. Lane closures will be used during daytime construction.


    Project Status: Complete

    Percent Complete: 100 %

    Current Information:

    Project is complete.

  • Date: 7/31/2014 12:27 PM

    Project 13: Grass Lake Rd From East of Grass Lake Bridge To IL 59

    Project Status: Scheduled

  • Date: 7/31/2014 12:27 PM

    Project 14: Russell Rd From IL 131 To Kenosha Rd

    Limits:
    Russell Rd From IL 131 To Kenosha Rd

    Project Status: Scheduled

    Current Information:

    Resurfacing work is scheduled to start in late July.

  • Construction Information:

    Dan Martinez, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

    Date: 7/31/2014 12:27 PM

    Project 15: Sand Lake Rd

    Limits:
    From Grand Ave (IL132) to US45 in Lindenhurst

    Project Description:
    The project consists of asphalt resurfacing and the installation of bike friendly shoulders. One lane traffic control will be used during daytime construction.


    Project Status: Scheduled

    Percent Complete: 0 %

    Current Information:

    Work will begin on August 11th, following LindenFest. The contractor is planning on starting with curb improvements.

  • Construction Information:
    Pete Torola, LCDOT
    Resident Engineer
    847.377.7400

    Additional Contact(s):
    Glenn Petko, LCDOT
    Engineer of Construction
    Resident Engineer
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400

    Lake County Traffic Info:
    lakecountypassage.com
     

    Date: 8/1/2014 8:01 AM

    Project 16: Lewis Ave From Dugdale St To IL 137

    Limits:
    From 500' north of Argonne Dr to IL137 in North Chicago

    Project Description:
    This project consists of asphalt resurfacing. Lane closures will be used during daytime construction.


    Project Status: Scheduled

    Percent Complete: 0 %

    Current Information:

    This project is expected to start in early September and is expected to  take about a month and a half to complete.

     

  • Date: 7/31/2014 12:27 PM

    Project 17: Midlothian Rd From South of Winchester Rd To IL 176

    Project Status: Scheduled

  • Construction Information:

    Paul Guardi, LCDOT
    Resident Engineer
    847.865.0151
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

    Date: 7/31/2014 12:27 PM

    Project 18: Long Grove Rd

    Limits:
    From Ela Road to east of Deer Valley Drive (west of Quentin Rd) in the village of Deer Park.

    Project Description:
    This project consists of asphalt resurfacing of pavement and bike lanes, replacement of driveway culverts and addition of side street drainage crossings.


    Project Status: Scheduled

    Percent Complete: 0 %

    Current Information:


    A preconstruction meeting with the contractor occurred July 14. The project is scheduled to begin Thursday July 24 with an anticipated end date of August 22. The work will include both the replacement of driveway culverts and side street drainage crossings. This will be followed by the milling and resurfacing of the road including the bike lanes.

    Drivers and bicyclists can expect delays due to intermittent daytime lane closures.

  • Construction Information:

    Scott Aho, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

    Date: 7/31/2014 12:27 PM

    Project 19: Aptakisic Road Adaptive Signal Control

    Limits:
    From Brandywyn Lane to Parkway Drive

    Project Description:
    Includes modification of the intersection cabinets and traffic detector configuration of existing traffic signals along Aptakisic Road in Lincolnshire and Buffalo Grove.


    Project Status: Scheduled

    Percent Complete: 0 %

    Current Information:

    Work is scheduled to begin mid-July and be complete in the fall of 2014

  • Date: 7/31/2014 12:27 PM

    Project 20: Gilmer Rd From Midlothian Rd To Fremont Center Rd

    Project Status: Scheduled

  • Date: 7/31/2014 12:27 PM

    Project 21: Gilmer Rd From Wildlife Way

    Project Status: Scheduled

  • Construction Information:

    Matt Mitchell, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

     

    Date: 7/31/2014 12:27 PM

    Project 22: Fairfield Rd

    Limits:
    North of IL60 to south of IL120 - Starting 0.3 miles north of IL60 to 0.2 miles south of Townline Rd in unincorporated Lake County.

    Project Description:
    This project consists of the removal and replacement of three retaining walls. One lane of traffic in each direction will be maintained during most of the construction.


    Project Status: Active

    Percent Complete: 50 %

    Current Information:

    Work on west side of Fairfield is complete. Contractor has now made a lane shift to the east and moved traffic to the west to allow work to be done on the east side of Fairfield.

    Expect scattered and periodic traffic delays due to temporary lane closures caused by construction activities.

  • Construction Information:

    Pete Torola, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

    Date: 7/31/2014 12:27 PM

    Project 23: Washington Street Drainage Project

    Limits:
    At southeast corner of Washington St and IL83

    Project Description:
    This project consists of repairing an existing pipe drain crossing under Washington St and the installation of new storm sewer along the south side of Washington St.


    Project Status: Active

    Percent Complete: 58 %

    Current Information:

    Contractor has finished storm sewer installation. Next items of work are landscape restoration and lining the existing pipe across Washington Street. Minimal traffic impacts are expected.

  • Construction Information:

    Scott Stalesky, LCDOT
    Resident Engineer
    847.377.7400

    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400

    Lake County Traffic Info:
    lakecountypassage.com

    Date: 8/7/2014 8:47 AM

    Project 24: Rollins Rd

    Limits:
    From Helendale Ave to Wilson Rd in unincorporated Lake County.

    Project Description:
    The project consists of asphalt resurfacing and installation of curb and gutter on south side of Rollins Rd and other drainage improvements. The project also includes installation of storm sewer, pavement widening, and the reconstruction of the existing bike path.


    Project Status: Scheduled

    Percent Complete: 0 %

    Current Information:

    Project scheduled to start August 11,2014.

  • Date: 7/31/2014 12:27 PM

    Project 25: Lewis Ave From Blanchard Rd

    Project Status: Scheduled

  • Date: 7/31/2014 12:27 PM

    Project 26: NS Bikepath From Union Pacific Railroad To East of US 41

    Project Status: Scheduled

  • Date: 7/31/2014 12:27 PM

    Project 27: Washington St From Atkinson Rd To Lancer Ln

    Project Status: Scheduled

  • Construction Information:

    Scott Aho, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

    Date: 7/31/2014 12:27 PM

    Project 28: Cedar Lake Rd From Washington St To S Rosedale Ct

    Limits:
    Washington Street to Park Road in Round Lake

    Project Description:
    This project installs a sidewalk and related items on the east side of Cedar Lake Rd


    Project Status: Scheduled

    Percent Complete: 0 %

    Current Information:

    Work is scheduled to begin in mid-summer and be complete in the fall of 2014.

  • Construction Information:

    Scott Aho, LCDOT
    Resident Engineer
    847.377.7400
     
    Additional Contact(s):

    Glenn Petko, LCDOT
    Engineer of Construction
    847.377.7400
    Al Giertych, LCDOT
    Assistant County Engineer
    847.377.7400
     
    Lake County Traffic Info:
    lakecountypassage.com

    Date: 7/31/2014 12:27 PM

    Project 29: Hunt Club Road Sidewalk

    Limits:
    From IL132 (Grand Ave) to West Brook Lane in Gurnee.

    Project Description:
    This project consists of the installation of sidewalk, pedestrian signals and crosswalks on the east side of Hunt Club Road.


    Project Status: Active

    Percent Complete: 80 %

    Current Information:

    The work consists of construction of a 5 foot wide concrete sidewalk along the east side of Hunt Club Road. Additionally the concrete median islands on the north side of the intersection will be modified to accommodate a pedestrian crossing for the north leg. Removing and replacing the stop bar and cross walk pavement markings is included.

    The project is expected to be complete this summer.

  • Date: 7/31/2014 12:27 PM

    Project 30: Aptakisic Rd From Weiland Rd To Bond St

    Project Status: Scheduled

  • Date: 7/31/2014 12:27 PM

    Project 31: Peterson Rd From W. of IL 83 To West of Alleghany Rd

    Project Status: Scheduled

  • Date: 8/1/2014 8:02 AM

    Project 32: Alleghany Rd

    Limits:
    From Peterson Rd To IL Rte 120

    Project Status: Scheduled

  • Date: 8/1/2014 8:02 AM

    Project 33: Washington St

    Limits:
    From West of Hainesville Rd to Haryan Way

    Project Status: Scheduled


Contact Us
Parking and Directions
Website Disclaimer
Site Map
Lake County, Illinois
847.377.2000
18 N. County Street
Waukegan, IL 60085
About Our County
PASSAGE
Alert Lake County
Find Help